Obstructed slab beams, beams shown on the drawings and not installed, breached termite protection. Pre-pour findings from Donnybrook builds.

  • Donnybrook 3064
  • 31 August 2026
  • 3 min read
Get a quoteTell us what you need and we will be in touch.

No obligation. We use your details for your quote and may contact you about it even if you don't finish.

Fully licensed & accredited

In short: The most useful pre-pour finding is not a mistake in the work. It is work that has not happened yet and was about to be covered in concrete.

Beams that were not there

We have recorded beams shown on the drawings and not installed at the time of inspection, and internal slab beams obstructed and not running continuous. A beam that stops where something is in the way is not the beam the engineer designed, and once the pour happens that is the slab you own.

Termite protection breached

Breached in several areas, on a Donnybrook job. At pre-pour that is a repair taking minutes. Afterwards it is a permanent set of entry points under a finished house.

Anti-ponding board

We have also photographed an anti-ponding board not installed under the sarking. It stops water pooling at the eaves where sarking meets the gutter line. Without it, water sits exactly where the roof is least able to deal with it.

The Whittlesea corridor

Olivine, Katalia, Kinbrook and the surrounding Donnybrook releases are among the fastest building in Melbourne's north. On programs that fast, the interval between a stage being ready and being covered is short enough that inspections have to be booked ahead.

Written by our local inspection team from work carried out in Donnybrook. Licensed building practitioners.

Blog

More from the Donnybrook blog

All posts →

Book a building inspection in Donnybrook

Instant online pricing for Donnybrook, or contact the booking team.

FAQ

Questions Donnybrook owners ask about this

What if the inspection finds work not yet done?

That is the most valuable outcome. It gets done before the pour instead of being buried.

Does this delay the pour?

Usually by hours at most. Most pre-pour items are corrected the same day.